Oman's OOG seeks more partners, supply for $15bln refinery in Indonesia

  • Apr 15, 2019
  • Zawya

Related Articles

* He said the cost of the project, which consist of a refinery and petrochemical plants, is $15 billion. Pertamina initially estimated the project cost at $10 billion

* The company aims to decide on financing source of the project within five months, Al Riyami said. The plant is scheduled to start operation around 2025-2026

* He added that OOG is also looking for more supply of crude oil for the 300,000 bpd refinery, preferrably from national oil companies

* OOG has signed memoranda of understanding with two local companies, PT Sanurhasta Mitra Tbk dan PT Meta Epsi Tbk, to build supporting facilities in Bontang, such as power stations, pipe infrastructure and water treatment for a combined value of $3 billion.

(Reporting by Wilda Asmarini, Writing by Fransiska Nangoy; Editing by Rashmi Aich) (([email protected]; +62 21 2992 7610; Reuters Messaging: [email protected]))